Rehabilitation works of the ODO-0CTCHERE water reservoir with development of 6 Ha of irrigated perimeter downstream in the district of KERE, Commune of Dassa-Zoumé

Main company:

NDC-GROUP-CAE

Contracting Authority:

Town hall of the commune of Dassa-Zoumé

Physical size

Structural work

Complexity

High

Period

March – June 2022

Brief description of the work done:

  • Installation of a 15.840 kWp solar system;
  • Wiring and Immersion of the pump ;
  • Installation of the protection box and the monitoring system ;
  • Wiring of the automatic starting and stopping of the pumping station ;
  • Pumping tests and commissioning.

We are positioning ourselves to become the N°1 Energy Efficiency intervention in Benin.